Sort
Tasks
|
 |
|
|
| Get large projects
under control |
| |
|
Milestones Professional offers
sorting in either ascending or descending order by any of the following:
|
|
|
IMPORTANT: |
|
Choose
Edit | Undo
Sort, to revert back to the original schedule after sorting.
Once you sort and then make a change to the schedule, you cannot
undo the sort. |
| |
| Click
here
for a tip on how to create a schedule that can be resorted to the
"original" schedule. |
|
|
Use this schedule as
a reference for the sorted schedules to follow: |
 |
| |
| |
|
|
Sort
task lines by date |
-
Choose Tools | Sort
Tasks | By Date.
-
Choose Ascending or
Descending order.
-
Sort by First Date or Last Date on the task line.
-
Optionally, choose to keep the Outline Structure of
the schedule.
Below, the dates
are in ascending order from earliest to latest according to the
first date on each task line: |
 |
 |
| |
| |
|
|
Sort
task lines by a selected column |
-
Highlight the key column for sorting, as shown below left.
-
Choose
Tools | Sort
Tasks | Using Selected Column as Key...
-
As shown below right,
choose Ascending/Descending and a type of column text.
-
Click OK.
|
|
 |
 |
| |
|
Below are the results of the sort, with employee names grouped in
alphabetical order. |
 |
| |
| |
|
| Sort
task lines by multiple columns |
-
Choose Tools
| Sort Tasks.
-
Choose
Using
Multiple Columns as Key to bring up the
Multi-Column Sort dialog
box.

- Click either
Sort in Ascending Order or
Sort in Descending Order.
- Click
All Task
Lines.
- Check up to three columns. (First
Key Column, Second Key
Column and Third Key
Column).
- Beneath each column that is
,
choose the column to be sorted.
- For each column being sorted, choose either
Text,
Numeric,
Currency, or
Date.
- Save the sort settings.
- Click OK.
Below are the results of the sort, with
tasks grouped by Project/Employee first, then in ascending order
based on the Budget value.
 |
| |
|