Outlining
|
 |
|
|
|
All Milestones software offers task outlining.
Milestones Simplicity offers a basic outlining capability for organizing your
tasks while Milestones Project Companion and Milestones Professional offer
additional functionality such as
task roll-up
and summary bars. This article discusses the basic outlining which is
common to all three products. |
|
|
|
The Outline Level SmartColumn lets you assign the
outline level for each task.
Outlining your project steps makes it easier to
show the sub-tasks for an individual task line. Tasks can be assigned a level
from 1 to 20, with 1 being the default value.
|
|
 |
|
The Outline Level SmartColumn displays the outline level (1-20)
of each of your project tasks. |
|
|
|
To add an Outline Level SmartColumn: |
| 1 |
Choose Insert | Column | Outline
Level. |
| 2 |
Double-click the column heading to
change its title and other properties. |
|
|
|
|
To change the outline level of a task: |
|
|
|
|
|
Indent column text based on outline level |
|
When outlining a schedule to show a hierarchy of
activities such as Project, Phase, Task, Sub-task; you may want to indent each
hierarchical level to set them apart from each other.

To set up a task column to be indented based
on outline level:
| 1 |
Double-click the column heading for
the column whose entries (text, values, etc.) you want indented based on
outline level. |
| 2 |
Double-click the column heading to
change its title and other properties. |
| 3 |
Under Indenting for Outlining, enter
an indent amount (.2 is an effective outline indention) next to Space
per outline level to indent column text. |
|